A308/A304 Fulham Road, London, Kensington And Chelsea
10 August — 12 August Traffic control (two-way signals)
Delays likely due to Streetworks
Install 16m Of 2 Poly Ducts In Carriageway,Install 4m Of 2 Poly Ducts In Footway at A308/A304
Responsibility: BT
EToN status: Planned work about to start
A304 Fulham Road, London, Hammersmith And Fulham
10 August — 14 August Some carriageway incursion
Delays possible due to Streetworks
11/081 - Install 2 X Pedestrian Countdown Units, Change Push Button Fronts, Reconfigure Controller For Pcat'S. 09:00-16:30. Tfl Requested To Close Crossing. Pedestrians To Use Crossing O/S 7 Fulham Broadway. at A304
Responsibility: Transport For London
EToN status: Planned work about to start
A308/A304 Fulham Road, London, Kensington And Chelsea
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Locate And Excavate 1 Blockage In Existing Duct at A308/A304
Responsibility: BT
EToN status: Planned work about to start
A308/A304 Fulham Road, London, Kensington And Chelsea
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Coredrill Footway Chamber To Connect A Client at A308/A304
Responsibility: Virgin Media
EToN status: Planned work about to start
A308/A304 Fulham Road, London, Kensington And Chelsea
10 August — 21 August Some carriageway incursion
Delays possible due to Streetworks
Install 4m Of 1 Way Poly Duct In Footway,Install 9m Of 1 Way Poly Duct In Carriageway. at A308/A304
Responsibility: BT
EToN status: Planned work about to start
A308/A304 Fulham Road, London, Kensington And Chelsea
10 August — 21 August Some carriageway incursion
Delays possible due to Streetworks
Install 4m Of 1 Way Poly Duct In Footway,Install 1 Nga Cab. at A308/A304
Responsibility: BT
EToN status: Planned work about to start
A308 King'S Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Replace 1 Jointbox Frame And Cover(S) (915mm X 445mm) In Footway at A308
Responsibility: BT
EToN status: Planned work about to start
A308 King'S Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Replace 1 Jointbox Frame And Cover(S) (1310mm X 610mm) In Footway at A308
Responsibility: BT
EToN status: Planned work about to start
A308 New King'S Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Install 2m Of 1 Way Poly Duct In Footway,Provide 1 Core Drill(S) Into Jointbox Or Building at A308
Responsibility: BT
EToN status: Planned work about to start
B317 North End Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
Rectify Reinstatement Defect In Footway. at B317
Responsibility: Thames Water
EToN status: Planned work about to start
Broomhouse Road, London, Hammersmith And Fulham
11 August — 13 August Some carriageway incursion
Delays possible due to Streetworks
- at -
Responsibility: National Grid Gas Plc
EToN status: Planned work about to start
Greyhound Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
- at -
Responsibility: Thames Water
EToN status: Planned work about to start
Greyhound Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
- at -
Responsibility: Thames Water
EToN status: Planned work about to start
Harwood Terrace, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
- at -
Responsibility: Thames Water
EToN status: Planned work about to start
Townmead Road, London, Hammersmith And Fulham
10 August — 12 August Some carriageway incursion
Delays possible due to Streetworks
- at -
Responsibility: UK Power Networks
EToN status: Planned work about to start

 

Information supplied by roadworks.org